SMC FRP Tank Installation Construction Plan

First, level the cement on the foundation level so that it is on the same plane. The error must not exceed ±0.5cm.
Second, the welding channel: channel steel welded according to the size of the tank, the size of the tank with the tank floor size, channel steel welding, the diagonal measurement size, the error is ± 0.5cm, and all the welds to be evenly connected, consistent seam .
Third, the installation of the bottom: According to the watermark on the tank description, arranged, connected to the bottom of the tank, while adding sealant between the veneer, with 10 bolts, so that the bottom seal is solid, when the bolt force To evenly increase the force, apply 3-4 times of force to each bolt. Do not use too much force at one time. Otherwise, cracks may occur due to uneven force.
Fourth, use the fixed angle iron to connect the bottom plate and channel steel, so that the tank box is more firmly fixed on the channel steel foundation.
V. Install each group: According to the number and description of the tank board, find out the number of each layer of the tank body, and separate them in advance, and then assemble the body with bolts. Set the tank board well, correct it, and use the body. Bottom to form a 90-degree angle, and add seals, tighten the bolts.
VI. Installation of lacing: The inner lacing shall be based on the dimensions of the tank and find the number and length of lacing. Use lacing boards to measure the tightening position of the lacing on the wire, drawing, punching, pulling on the wire, and tightening, so as to balance the lacing flatness with the tank body. If there is a large error between the box and the lacing, the error can be adjusted by adjusting the tightening degree of the bolt until the error is minimized.
7. Install the cover plate: Install the top cover plate of the water tank lastly and evenly tighten the bolts. Do not use too much force or too little. After adjusting all the fasteners of the water tank, open the position according to the drawing and open the water pipes. Flange to dock the valve.
VIII. After the water tank is installed, carry out unified inspection and adjustment. The test water does not leak to be qualified.

Hospital Sliding Door

Door panel: door panel is made of stainless steel 304 with no frame. Core materials are paper honeycomb, aluminum honeycomb, PU, EPS and etc. The installation sites of door lock, door closer and hinge are reinforced with square tubes of more than1.5mmthickness which are compression moulded by special technology.


Door frame: it is made of completely stainless steel 304. The connection types with wallboards are double-clip type and aluminum connection. The former is applied mostly to machine made wallboard and the latter hand made wallboard. The accessories are double window and lift type sweeping bar. The lock can be famous door lock or the owners can select lock brands themselves.

Specification: common sizes 800X2100, 900X2100, 1500X2100 or1800X2100, can customize to customers` requirements, the materials can be selected according to customers` requirements such as306Lor other special materials.


Features: the stainless steel 304 door we produced are of elegant appearance, sturdy and durable, acid and rotting resistance and thermal insulation. It is the first choice for high-end projects at home and engineering concerning foreign affairs that requires for anticorrosion and high quality such as electronics factory and food factory


Hospital Sliding Door,Hospital Automatic Sliding Door,Hospital Sliding Glass Door,Hospital Sliding Ward Door

Shenzhen Hongfa Automatic Door Co., Ltd. , https://www.hfhighspeeddoor.com